The BSP Project started on April 30, 2019, and being funded by the Millennium Challenge Corporation (MCC) and Ghana Government, under the Ghana Power Compact Programme.
Upon completion, the BSP Project would supply reliable electricity to 350,000 residents within its catchment area, including businesses, public institutions and health facilities.
A statement issued by the Communications and Outreach Unit of Millennium Development Authority (MiDA) and copied to the Ghana News Agency in Accra, said the six major transformers for the Project arrived in the country from Turkey on April 27 and May 4 respectively.
The transformers, which come in two sizes, 145 MVA and 39 MVA, would support the operations of GRIDCo and ECG for efficient and reliable power supply in the beneficiary communities.
The statement said the transformers had been subjected to Factory Assessment Tests in the presence of the officials of MiDA, ECG GRIDCO and other stakeholders committed to the project.
It said MiDA and the Project Contractors have put in place the necessary safety protocols to safeguard the health of workers undertaking the construction works and residents within the project catchment area.
---GNA


It is not a crime if central banks miss IFRS standards – Dalex CEO
Allow BECE candidates to use calculators — Effia MP urges Minister to reconsider...
We will make University of Environment and Sustainable Development a citadel of ...
Education Minister urges WAEC to review transportation of exam materials
Ghana borrows GHS20.48 billion from treasury bill auctions in April 2026
Fresh shooting shatters fragile calm in Nkwanta South, Okada rider shot
Ghana: Four PDS officials arrested over alleged transfer of Gh¢850million from E...
Bekwai NPP aspirants threaten demonstration over alleged vetting irregularities
Asantehene warns Boankra Inland Port delays threaten public funds and investor c...
Ghana Police Service suspends five officers over alleged misconduct in viral vid...