The Alliance of Civil Society Organisations (CSOs) working on Extractives, Anti-Corruption, and Good Governance have expressed concern over plans by the Energy Ministry to relocate the Ameri Power plant.
The Energy Ministry led by Minister Matthew Opoku Prempeh is planning to relocate the Ameri Plant from Takoradi to Kumasi to ensure a stable supply of power to the middle belt.
As revealed by the Africa Centre for Energy Policy (ACEP), although the relocation of the plant from Takoradi to Kumasi according to the Energy Ministry will cost $35.6 million, the cost involved is actually $25.48.
“The Minister quotes $35.6 million as the cost of the relocation in his 17th December 2021 letter to VRA. However, ACEP has sighted the original proposal from Mytilineos SA dated 22nd March 2021 to the Ministry, quoting $25.48 million for the same.
“Instead of negotiating the proposal of the sole-sourced offer downwards, the contract cost has instead increased by 40 percent. It is unclear what accounts for such a quantum leap from the proposal amount by Mytilineos SA,” ACEP recently disclosed in a statement.
Following that revelation, Energy Minister Matthew Opoku Prempeh in an interview alleged that ACEP is only against the relocation of the Plant because it has something against the people of Kumasi.
Reacting to the claims at a press conference in Accra today, the Alliance of CSOs working on Extractives, Anti-Corruption, and Good Governance has implored the Minister to desist from personal attacks on ACEP.
Accusing the Minister of diversionary tactics, the CSOs want him to instead respond to the real issues at hand with a focus on how best to solve the challenges facing the energy sector.
“We demand that the Minister of Energy should constructively engage on the core issues raised rather than divert public attention from them. We understand that the overall aim is to stabilize power in the middle belt and hence discussion should focus on how to efficiently achieve this objective,” Executive Director of the Centre for Extractive and Development, Africa, Samuel Bekoe told the media today.
Samuel Bekoe
He stressed that it is the view of the CSOs working on Extractives, Anti-Corruption, and Good Governance that a competitive bidding process should be used to award the contract for the relocation of the Ameri Plant.
Through that, he says the country can save cost to reduce the growing debt crippling the energy sector.
“The Ministry of Energy should revisit the concerns on the need for adopting a competitive bidding process to accommodate local contractors to achieve the most optimal contract cost,” Samuel Bekoe shared.
He added, “We maintain that the Minister should consider other options which we believe are far optimal option than the attempts to relocate plants and its attendant unnecessary cost additions. For instance, retooling National Interconnected Transmission Systems (NITS).”
Additionally, the CSOs working on Extractives, Anti-Corruption, and Good Governance want Cabinet and Parliament to assume critical responsibility for the efficient planning of the sector.
The CSOs argue that these decisions among others have contributed to the current economic difficulties being faced in the country.


Iran says closed Strait of Hormuz as US deal hits obstacle ahead of Swiss talks
World Cup 2026: Brobbey, Gakpo score braces as rampant Netherlands crush Sweden
'What power do you have to collapse NPP you did not build?' – Awal Mohammed jabs...
Chaos at Central University as vendors demand refunds after SRC Week cancellatio...
GMet issues severe weather alert for Northern Ghana as heavy rainstorm approache...
Ken Ofori-Atta is the first Ghanaian minister to use sickness to flee from accou...
Family demands justice for 14-year-old girl allegedly raped, killed in Binaba
Trump cuts HIV funding to South Africa
88 dilapidated buildings marked for demolition in Sekondi-Takoradi
Police crack suspected robbery network in Ashanti South, two suspects killed in ...