Effasu (W/R) March 10,GNA- The "Osagyefo" Power Barge meant for the generation of electricity at Effasu-Mangyea in the Jomoro District of the Western Region, berthed at the Effasu Mangyea mini harbour on March 7.
The barge had remained at the Sekondi Naval base since October 13, 2002 after a three-week trip from Italy where it was built.
Mr Martin Nyamekye-Ackah, Jomoro District Chief Executive who inspected the barge said its arrival at the harbour was an indication that government had not abandoned the project.
Mr Joseph B. Aidoo, Regional Minister told the Ghana News Agency in an interview in Sekondi that the delay of the barge at the Sekondi Naval Base was due to the high and unfavourable sea tide at Effasu-Mangyea. The barge which has two single cycle heavy-duty gas turbine units could produce a total of 125 megawatt of power.
The barge was procured in 1995 through the Ghana National Petroleum Corporation credit facility from the Overseas Economic Cooperation Fund of Japan at 12.195 billion Japanese Yen (120 million Dollars). It weighs about 10,900 tonnes and is 77 metres long with 161 kilovolts gas insulated switch-gear, a control room, fire fighting and miscellaneous auxiliary systems.
The transmission lines, communication facilities and other necessary works have been completed.


ACFO II Semey Mawuko bows out after 37 years in GNFS
Adwoa Safo is the rightful successor to late Apostle Kwadwo Safo — Family
We do not recognize Akofena as leader of Kristo Asafo Mission — Kantaka family
US cracks down on visa holders accused of abusing system and defrauding citizens
IMANI stopped asking questions when the NDC took office – Miracles Aboagye
Mother and son buried after Cape Coast rain disaster, NADMO orders building chec...
Four medical laboratories shut down in Bolgatanga over regulatory breaches
Dismiss Kennedy Agyapong from NPP — Agyenim Boateng
Asantehene receives rousing homecoming at Prempeh Airport after Europe, North Am...