The Managing Director (MD) of the Accra-Kumasi Expressway Limited, Engineer Francis Ahlidza, has announced that the 175.6-kilometre Accra-Kumasi Expressway is expected to be completed by December 2028.
Engineer Ahlidza said the project is being structured around a two-year construction period, with physical works expected to commence in January 2027 following the completion of the procurement and contractor selection processes.
Speaking on the Citi Breakfast Show on Tuesday, September 15, Engineer Ahlidza disclosed that the procurement process for the contractors has already commenced, with firms being invited to express their interest in undertaking the major road project.
He explained that the selection process will be conducted in two stages and will involve international competitive procurement to ensure that qualified firms are selected for the project.
“We are working with a two-year construction period starting at the end of this year. We have started the procurement process by requesting for firms to express interest which is an international competitive process but we will do that in two stages.
“We expect to close this at the end of the year so that the contractors can start working in January 2027 and complete by December 2028.”
Engineer Ahlidza's timeline means that, barring significant delays in the procurement and construction processes, motorists could begin using the completed expressway by the end of 2028.
The announcement comes a day after the official right-of-way handing-over ceremony for the project was held on Monday, September 14.
The Accra-Kumasi Expressway is expected to significantly transform road transportation between the two major cities and improve connectivity along one of Ghana's busiest economic corridors.
The 175.6-kilometre road project is also expected to improve the movement of people and goods, reduce travel times and enhance road safety for motorists who regularly use the Accra-Kumasi route.
According to details provided on the project, the expressway will feature eight grade-separated interchanges, 11 vehicle overpasses and 55 mainline bridges.
-Citinewsroom



2027 Budget: ‘Another round of slogans with no jobs’ – Afenyo-Markin
Women's Development Bank to begin operations in early 2027 – Ato Forson
Govt to settle US$590m Eurobond and domestic bond obligations by December 31 – A...
Govt allocates GH¢1bn to complete 35 Agenda 111 hospitals in 2027
Ato Forson outlines eight pillars of government's US$10bn economic transformatio...
Govt allocates GH¢600 million for construction of 10 regional stadia
Government rules out new taxes in 2027, targets GH¢323.4bn revenue
2027 Budget: Gov't to improve revenue collection without introducing new taxes –...
New Economy to help Ghana process more of its resources locally – Ato Forson
[Full text] Ato Forson presents 2027 budget in Parliament