The President of the Republic, Nana Addo Dankwa Akufo-Addo, has inspected ongoing work on construction of the Kumasi International Airport, which, according to the contractor, is currently 77% complete, and is expected to be completed in June 2022.
President Akufo-Addo visited the site of the construction on Friday, 1st October 2021, when he commenced his 4-day working visit to the Ashanti Region, as part of his annual working visits to all the Regions of the country.
It will be recalled that on 6th June 2018, the President cut the sod for the commencement of work on Phase Two of the Kumasi Airport Project, where he indicated that “the expansion of this airport is a critical part of government’s vision to expand the frontiers of the aviation industry in the country, and to realise the dream of making Ghana an aviation hub in West Africa.”
Inspecting work on the site, the President was told that the terminal building was 88% complete, the road network 93% complete, the Apron 89% complete, with the air traffic control and rescue and firefighting services 53% complete.
The scope of work include the extension of existing runway pavement from 1,981 metres to 2,320 metres, the construction of a new taxi link and apron, two new apron parking stands, aeronautical ground lighting systems, the design and building of a terminal with the capacity to handle eight hundred thousand passengers per annum, an 11 MW substation, as well the provision of new bulk utility (electricity, water, sewage treatment system, internet etc.) services, independent of the existing utility services for the existing airport facilities.
Phase three (3) of the project involves the construction of the air traffic control building, a fire building station, as well as the expansion of the existing runway pavement. The construction of the fuel farm is to be funded by GOIL.
With the project being constructed by Messrs. Contracta Construction UK Limited, the total project sum is €124.9 million, with financing from Santander, Deutche Bank, and UKEF.
President Akufo-Addo expressed satisfaction with the progress of work undertaken so far, and charged the Ministry of Transport as well as the Contractor to ensure that the October 2022 deadline for completion is met.



FAKE: Deputy Minority Leader returns GHS70,000 received from vetting of Minister...
'I will die with integrity than be corrupted by galamsey' – Lands Minister
'The people who benefit never die' – Kwesi Pratt on Gomoa, New Winneba land disp...
Cement price hike looms as manufacturers introduce GH¢12 clinker demurrage surch...
BOGISS defilement case: Security guard allegedly lured 14-year-old student with ...
Police recover AK-47, 28 rounds of ammunition; suspect killed in Binduri operati...
Your conduct is undeserving of a leader of the bench - John Boadu slams Chief Ju...
Port inspection delays is increasing cost of doing business – ICC Ghana
Works Minister pushes for shorter timeline for Kaneshie–First Light Road Project
Driving must be studied from primary to university – Ada West DCE proposes
Comments
the kumasi international airport after completion should be named j b dankwah international airport or akuffo addo international airport.