Work starts on components for Ghana's second FPSO at new Sekondi yard

By Myjoyonline.com
Work starts on components for Ghana's second FPSO at new Sekondi yard
18.12.2014 LISTEN

A new fabrication facility for the oil sector has opened at Sekondi in the Western Region. The yard has been built by Tullow Oil to fabricate components for the TEN Project, Ghana's next major oil development, on land leased from the Ghana Navy.

Work at the site has started on the fabrication of nine anchor piles for Ghana's second floating production and storage (FPSO) vessel, which will start producing oil from the Tweneboa, Enyenra and Ntomme (TEN) fields in mid-2016.  The 122 tonne, 23 metre high steel cylinders will anchor the FPSO to the seabed, keeping it in place during its lifetime. 

The yard provides new fabrication capability, enabling more work to be done in-country. This will be the first time that FPSO anchor piles have been constructed in Ghana.  

Following the completion of the anchor piles in April 2015, the facility will be used to fabricate jumper spools for the TEN Project, which will connect subsea production equipment on the seabed.

Tullow Ghana Ltd General Manager Charles Darku commented:  “It's fantastic to see work has started at this new facility.  We are grateful to the Navy for allowing us to lease the land. The TEN Project is making good its local content commitments and I'm very proud that Tullow is leading the first project to fabricate important FPSO components in Ghana.”  

Alex Mould, CEO of the Ghana National Petroleum Corporation, said: “As one of the TEN Partners, we are pleased to be associated with the efforts that the field Operator, Tullow, is pursuing. It is tangible evidence that we are delivering on the commitments made in the TEN Development Plan, approved by the Minister of Energy & Petroleum, and also provides Ghana with a sustainable legacy that will support not just the TEN and Jubilee developments, but future oil projects as well. We congratulate all associated with this significant achievement.”

A second new fabrication yard, also commissioned to fabricate components for the TEN Project, will soon open in Takoradi port. Being built by Subsea7, this facility will be used to fabricate anchor piles for subsea manifolds.  

Working in collaboration with the Petroleum Commission, the TEN Project is committed to maximising the amount of work undertaken in Ghana. Earlier this year, module support stools for the FPSO were fabricated by Seaweld Engineering Ltd and Orsam Ltd in Tema and Takoradi, subsea mud mats are currently being fabricated by Harlequin International Ghana Ltd and Accra-based Hydra Offshore Group is supplying engineering services to the project. 

TEN Project
The TEN fields (Tweneboa, Enyenra and Ntomme) lie in the deepwater Tano block, around sixty kilometres offshore Ghana.  The reservoirs are spread over 800 square kilometres and lie in water depths of between 1,000 and 1,800 metres. 

Development of the TEN Project is being led by Tullow Oil, with partners Ghana National Petroleum Corporation, Kosmos Energy LLC, Anadarko Petroleum Corporation and PetroSA. 

The TEN Development Plan was approved by the Government of Ghana in May 2013 and requires the drilling and completion of up to 24 development wells. These will be connected through subsea infrastructure to a Floating, Production, Storage and Offloading (FPSO) vessel currently under construction in Singapore.  

First oil from the TEN fields is scheduled for mid-2016, and the nominal production capacity of the FPSO is 80,000 barrels of oil per day.    